Activities & Achievement


Activities & Achievement

 

                                                                                                                                                         Update on 26/09/2024

 

                                               Summary of commissioning of sections during 2024-25:

S.N.

Name of the Project

Section

KMs

Date of commissioning

1

Bilaspur- Jharsuguda 4th line

Bilaspur- Gatora

8.00

30.4.24

2

Rajnandgaon- Nagpur 3rd line

Paniajob- Bortalao

8.00

9.5.24

3

Anuppur- Katni 3rd line

Badhwabara-Ghunguti

13.00

5.7.24

4

Rajnandgaon- Nagpur 3rd line

Kamptee- Kalumna

7.72

18.9.24

Total

36.72

Upto 18.09.2024

 

                                                                                Construction Budget (Fig in Cr.

P.H.

Year  2023-24

Year  2024-25

BG-2023-24

FME

2023-24

Exp up to Aug

’ 23

Cum Exp 2023-24

BG-2024-25

New BG-2024-25

Exp. Aug’24

Cum Exp 2024-25

% on  New BG

11

105.65

189.12

81.96

189.16

480.00

695.00

14.92

140.34

20.19

14

86.51

80.79

27.71

83.24

100.00

35.00

8.06

21.27

60.77

15

1810.42

1538.13

572.26

1545.66

2176.28

1649.14

100.41

716.34

43.44

16

107.71

100.14

31.62

102.69

69.11

69.11

1.02

18.75

27.13

30

23.87

114.00

24.17

116.16

36.74

36.74

2.80

30.78

83.78

36

18.78

23.76

18.78

23.76

0

0

0

0

0.00

42

10.30

12.75

1.76

12.67

5.50

5.50

0.02

2.58

46.91

51

0

0.18

0

0.18

0.006

0.006

0

0

0.00

Total

2163.24

2058.87

758.26

2073.52

2867.63

2490.50

127.24

930.18

37.35

Source : South East Central Railway (SECR) Last Reviewed : 26-05-2026