Summary of Targeted Works – 2022-23
Name of the Project | Section | KMs | TDC | Revised TDC | NI Involved 2022-23 | Completed till date | TDCs for remaining NIs |
Bilaspur-Jharsuguda 4th Line | Himgir-Belpahar | 13 | Apr’22 | Commissioned | 1 | 1 | - |
Brajrajnagar-Jharsuguda | 10.5 | Jun’22 | Commissioned | 2 | 1 | 1 (by SER) Jharsuguda – Dec’22 |
Gatora-Latia | 18 | Oct’22 | Dec’22 | 3 | 2 | Gatora – Jan’23 |
Sakti-Jharadih | 10 | Jan’23 | Jan’23 | 2 | 0 | Jharadih – Feb’23 |
Sakti – Feb’23 |
Jamga-Himgir | 20.5 | Dec’22 | Jan23 | 3 | 1 | Jamga – Feb’23 |
|
ACBPL – Dec’22 |
Saragaon-Sakti | 19.5 | Feb’23 | March’23 | 2 | 0 | Saragaon – Mar’23 |
Baraduar – Mar’23 |
Rajnandgaon-Kalumna 3rd Line | Kachewani-Tumsar Road | 27.12 | Aug’22 | Commissioned | 2 | 2 | - |
Tharsa-Salwa | 13 | Jan’23 | Jan’23 | 2 | 1 | Chacher – Jan’23 |
Bhandara-Tharsa | 24.7 | Dec’22 | Dec’22 | 3 | 2 | Tharsa – Dec’22 |
Dhanoli-Gudma | 18 | Dec’22 | Feb’23 | 3 | 0 | Dhanoli – Jan’23 |
Aamgaon – Mar’23 |
Gudma – Mar’23 |
Gangajharih-Kachewani | 8.46 | Nov’22 | Dec’22 | 1 | 0 | Gangajhari – Feb’23 |
Kanhan-Kamptee | 4.54 | Jan’23 | March’23 | 2 | 0 | Kanhan – Mar’23 |
Kamptee – Mar’23 |
Anuppur-Katni 3rd Line | Amlai-Burhar-Singpur | 22.4 | Jul’22 | Commissioned | 3 | 3 | - |
Umaria-Chandia | 18.9 | Nov’22 | Feb’23 | 3 | 0 | Umaria – Mar’23 |
Lohra – Dec’22 |
Chandia – Mar’23 |
Singhpur-Shahdol | 5.9 | Dec’22 | Feb’23 | 1 | 0 | Shahdol – Mar’23 |
Shahdol-Badhwabara | 8 | Feb’23 | Feb’23 | 1 | 0 | Badhwabara – Feb’23 |
Chandia-Rupuand | 16.8 | Feb’23 | Feb’23 | 1 | 0 | Vilayatkala – Dec’22 |
Fly Over at Bilaspur | Bilaspur-Uslapur Flyover | 10.5 | Dec’22 | Dec’22 | 2 | 0 | Uslapur – Jan’23 |
Bilaspur – Feb’23 |
MandirHasaud-Kendri New Line | MandirHasaud-Kendri | 20 | Jan’23 | Jan’23 | 3 | 2 | Kendri – Dec’22 |
Kendri-Dhamtari&Abhanpur-Rajim GC | Kendri-Abhanpur | 6 | Jan’23 | Feb’23 | 1 | 0 | Abhanpur – Feb’23 |
| Total Railway Target | 295.82 | | | 41 | 15 | |