Power line -
Cable shifting of old FOB of DPH, BYL, DGS, HN, SLH station and electrification & illumination work of new FOB has been done by departmental staff.
200 Nos 16W LED Light has been provided including wiring in pit at ELS & MEMU shed / Bhilai.
Solar water heater of 100LPD capacity installed in 23 Nos. Type –III, IV & V Officer Bungalow in WRS Colony Raipur and 15500LPD capacity Solar Water Heater installed in various rest houses, RPF Barrack and Running Room (total 31700LPD).
13 nos. Air cooling was installed in RPF Barrack (Durg-20000 CFM-02 Nos., WRS-10000 CFM-04 Nos., Bhatapara-10000 Cfm-02 Nos., BMY-10000 CFM-02 Nos and Bhilai-10000 CFM-03 Nos) and rewiring has been done at RPF Barrack Bhilai and BMY.
35 nos Type-II Quarters electrification done at DRZ and street light provision done.
Two 11KV track crossing overhead line at J-cabin & Memu shed and G-cabin & Bhilai at Up Main line were removed and final termination was done by Stay & Gay arrangement departmental staff at DP at BMY yard.
New 11/0415 KV-100 KVA substation in Lakholi station has been charged by RVNL and commissioning of cabling and distribution panel has been done at MNDH.
New 3 phase CSPDCL connection has been taken for 7.5HP pump at Mohabhatta Gate (for Belha station water).
5 Span interrupted LT overhead lines has been Shifted from Sarona station to AIIMS.
03 Nos 2HP Additional Pump at TLD, SKO, BPHB, 01 Nos 5HP in BXA, 01 Nos 7.5HP For Bilha Station at Mohabhatta Gate, 01 Nos 2HP Additional Pump MDH, 02 Nos 10HP Additional DIWATTERING Pumps RUB at LC no 432 & 441, 03 City 10HP additional DIWATTERING pump H cabin RUB at LC no 433-434, Amanaka RUB and WRS filter house ,02 nos 1.0HP submersible pump at Dhaora bhata and davanbod L/C Gate installed by departmental staff.
02 Nos. 100HP Pump of WRS Filter House was automated by soft starter and Automation operation of Quick Watering System of Raipur was done by GSM System.
04 nos RUB illuminated and dewatering pump provided.
Old 11KV VCB panel changed with new one in 33 KV receiving sub station at DLS/R .
SS No.-20/BMY-250KVA Transformer augmented by 500KVA.
New 2X250KVA, 11 / 0.415KV substation work completed of Durg and line charged by CSPDCL.
Air-conditioned and Train light
303 nos (44 AC and 191 TL. + LHB (SS-1&SS-2) -68 (AC-31 & Non AC-37) coaches IOH done in Durg Coaching Depot.
LED light retrofitted done in 101 coaches (31 AC and 70 TL)
55 coaches were converted into isolation wards for prevention of corona virus.
DRM Salon old battery replaced with 500AH capacity new set .
HSD Oil Savings-329955 and consumption-46083 Liters in HOG Operation.
All 13 Primary Rack Trip Maintenance and charging has been done for 18 Rack