(i) Charging of Dumrikhurd-Ramtek
Dumrikhurd-Ramtek has been commissioned & energized on 11.04.2015.
(ii) Charging of RUR connecting APML Siding to Dn Main Line
RUR connecting APML Siding to Dn Main Line total of total 3.852 TKM has been commissioned & energized on in month of May’15.
(iii) Charging of Koradi siding
Newly electrified line no. 2, 3 4, 5, 6 & 7 of Koradi TPS expansion project at Koradi total of total 11.519 TKM has been commissioned & energized on in month of July’15.
(iv) Commissioning of new SCADA system (M/s Merit make) in place of existing SCADA system on 20th April’15.
(v) Charging of ATs
02 no. 25KV/240, 25 KVA ATs provided and energized in place of existing 10 KVA ATs at Kachewani station yard to cater to the additional load of M/s APML siding on the month of 30th April’15. In connection with automatic signaling work between Gondia-Nagpur, 06 no. 25 KV/240V, 10 KVA AT provided and energized for providing power supply to S&T goomties in which 03 no. in DKU –RTK section and 01 in each of KNHN-DKU, K-TMR, K-BRD section on month of July’15.
(vi) Condemnation of Redundant BT Masts
In this year, total 246 nos. BT Masts (86.10 MT) which were redundant since 1995-96 after the removal of Booster Transformers have been condemned & proposed for disposed off on ‘as is where is’ through GSD/Raipur. Work completed.