Update on 26/09/2024
Summary of commissioning of sections during 2024-25:
S.N. | Name of the Project | Section | KMs | Date of commissioning |
1 | Bilaspur- Jharsuguda 4th line | Bilaspur- Gatora | 8.00 | 30.4.24 |
2 | Rajnandgaon- Nagpur 3rd line | Paniajob- Bortalao | 8.00 | 9.5.24 |
3 | Anuppur- Katni 3rd line | Badhwabara-Ghunguti | 13.00 | 5.7.24 |
4 | Rajnandgaon- Nagpur 3rd line | Kamptee- Kalumna | 7.72 | 18.9.24 |
Total | 36.72 | Upto 18.09.2024 |
Construction Budget (Fig in Cr.
P.H. | Year 2023-24 | Year 2024-25 |
BG-2023-24 | FME 2023-24 | Exp up to Aug ’ 23 | Cum Exp 2023-24 | BG-2024-25 | New BG-2024-25 | Exp. Aug’24 | Cum Exp 2024-25 | % on New BG |
11 | 105.65 | 189.12 | 81.96 | 189.16 | 480.00 | 695.00 | 14.92 | 140.34 | 20.19 |
14 | 86.51 | 80.79 | 27.71 | 83.24 | 100.00 | 35.00 | 8.06 | 21.27 | 60.77 |
15 | 1810.42 | 1538.13 | 572.26 | 1545.66 | 2176.28 | 1649.14 | 100.41 | 716.34 | 43.44 |
16 | 107.71 | 100.14 | 31.62 | 102.69 | 69.11 | 69.11 | 1.02 | 18.75 | 27.13 |
30 | 23.87 | 114.00 | 24.17 | 116.16 | 36.74 | 36.74 | 2.80 | 30.78 | 83.78 |
36 | 18.78 | 23.76 | 18.78 | 23.76 | 0 | 0 | 0 | 0 | 0.00 |
42 | 10.30 | 12.75 | 1.76 | 12.67 | 5.50 | 5.50 | 0.02 | 2.58 | 46.91 |
51 | 0 | 0.18 | 0 | 0.18 | 0.006 | 0.006 | 0 | 0 | 0.00 |
Total | 2163.24 | 2058.87 | 758.26 | 2073.52 | 2867.63 | 2490.50 | 127.24 | 930.18 | 37.35 |