Achievement and Highlights of S&T department, Nagpur Division for the month of Dec’24
- System integrity testing have been done at following stationsin the month of Dec’24: -
S.N. | Station | Date of Completion |
1 | LTA | 14.12.24 |
2 | NWA | 21.12.24 |
3 | PDE | 30.12.24 |
4 | PNJ | 31.12.24 |
- Offline Safety seminar held at following stations in the month of Dec’24.
S.No. | Station | Topic | Date of Seminar | No. of staff attended |
1 | Samnapur | Unsafe practices in relay room, Upkeep of signaling gears at gates & stations, Disconnection & reconnection. | 11.12.24 | 08 |
2 | Mundikota | Unsafe practices in relay room, Upkeep of signaling gears at gates & stations, Disconnection & reconnection. | 31.12.24 | 07 |
- Power operated electric lifting barrier boom has been replaced at Balaghat station of LC gate GJ-36 at km 1042/3-4 on22.12.24.
- Earth Leakage Detector have been installed at Lamta & Palari stations on 13.12.24 & 19.12.24 respectively.
- Replacement of IRS point machine by Thick Web Switch at Following stations in theMonth of Dec’24.
S.N | Station | Pt . No. | Date of Replacement | S.N | Station | Pt . No. | Date of Replacement |
1 | DGG | 104A | 06.12.24 | 5 | SAL | 102B | 17.12.24 |
2 | BRD | 102B | 10.12.24 | 6 | AGN | 151A | 25.12.24 |
3 | G | 121A | 16.12.24 | 7 | G | 104B | 27.12.24 |
4 | KP | 101B | 28.12.28 | | | | |
- Wornout Ground connection of point machine have been replaced at following stations in the month of Dec’24.
S.N | Station | Pt . No. | Date of Replacement |
1 | KAV | 106B | 22.12.24 |
2 | KAV | 108B | 22.12.24 |
3 | KAV | 105 | 23.12.24 |
4 | KAV | 112A | 28.12.24 |
- Wornout Tongue rail have been replaced in coordination with Engg. Department at following stations in the month of Dec’24.
S.N | Station | Pt. No. | Date of Replacement |
1 | KWN | 113A | 06.12.24 |
2 | TRO | 153A | 21.12.24 |
- For improving reliability of track circuit, 27 nos. (As on 31.12.2024) of glued joints have been replaced in association with Engg. Department in the month of Dec’2024.
- New IPS battery (200AH) second set installed at Chiraidongri station on 31.12.24.
- Old IPS battery set has been replaced with new battery set at the following station/LC Gate in the month of Dec’2024:
SN | Station/LC | Nos. of batteries | Capacity | Date of replacement |
1 | Gangajhiri | 55 | 200AH | 22.12.24 |
| Total | 55 |
- Secondary cells have been replaced with new cells at the following stations in the month of Dec’24.
SN | Station | Nos. of batteries | Capacity | SN | Station | Nos. of batteries | Capacity |
1 | SONR | 9 | 80AH | 11 | VNK | 6 | 80AH |
2 | NDNI | 6 | 80AH | 12 | BMP | 18 | 80AH |
3 | GJ | 1 | 80AH | 13 | WDG | 51 | 80AH |
4 | TMR | 1 | 80AH | 14 | MNU | 3 | 80AH |
5 | AJU | 48 | 80AH | 15 | NIR | 9 | 80AH |
6 | BAKL | 6 | 80AH | 16 | NAB | 27 | 80AH |
7 | G | 9 | 80AH | 17 | DEW | 32 | 80AH |
8 | PTS | 6 | 80AH | 18 | PDE | 9 | 80AH |
9 | GNL | 21 | 80AH | 19 | ITR | 6 | 80AH |
10 | SNV | 36 | 80AH | | | | |
Total | 304 |
- The New Internet/ Railnet connectivity have been provided at following location in the month of Dec’2024.
i)Personnel (Electrical/bill) - 1 no
ii)Mechanical (Diesel/shed) - 1 no.
- The 6Quad & OFC cable have been replaced at the following locations in the month of Dec’2024.
Section | Location | Purpose & Quantity |
GNS- VNK | Km. No. 1155/4-9 | For defective 6 quad cable replacement 250 Mtrs. |
BSNL DP- Rly stn RTK | RTK Railway stn. | Total cable laying 360 Mtrs. |
- The Periodical testing of Wakie Talkie testing of following Guard/Driver lobby have been conducted in the month of Dec’ 2024.
i) CWA- 02.12.2024.
ii) NIR- 16.12.2024.
III) JBP - 26.12.2024.