Achievement and Highlights of S&T department, NGP Division for the month of
July,2023
1.Yard modification in connection with 3rd line work has been done at Gudma station (72 routes) in Nagpur-Durg section commissioned on 18.07.2022 by construction/NGP unit for provision of Electronic interlocking (EI) of M/s Hitachi make with Distributed architecture, hot standby, Dual VDU arrangement, MACLS arrangement, standard II R interlocking, complete track circuiting, IPS, Data logger, UFSBI, Fire alarm, ELD & Fuse Alarm system. S&T/Open line was actively involved and extended all the assistance required during every stages of this work.
2.Yard modification in connection with 3rd line work has been done at Kamptee station (86 routes) in Nagpur-Durg section commissioned on 25.07.2022 by construction/NGP unit for provision of Electronic interlocking (EI) of M/s Hitachi make with Distributed architecture, hot standby, Dual VDU arrangement, MACLS arrangement, standard II R interlocking, complete track circuiting, IPS, Data logger, UFSBI, Fire alarm, ELD & Fuse Alarm system. S&T/Open line was actively involved and extended all the assistance required during every stages of this work.
3.System integrity testing have been done at following stations in the month of July’23: -
S.N. | Station | Date of Completion |
1 | Mulmarora | 08.07.23 |
2. | Gudma | 16.07.23 |
3. | Kamptee | 24.07.2022 |
4.To improve reliability of point operation, old worn-out point machines has been replaced at following station in July’2023:
S.N | Station | Pt. | Date of Replacement |
1 | Birsola | 22B | 06.07.23 |
2 | Chacher | 57A | 15.07.23 |
5.Wornout Ground connection have been replaced at following stations in the month of July’23:
S.N | Station | Pt. No. | Date of Replacement |
1 | Birsola | 22B | 06.07.23 |
2 | Amgaon | 41A | 16.07.23 |
3 | Rewral | 151A | 26.07.23 |
6.Wornout Tongue rail have been replaced in coordination with Engg. Department at following stations
in the month of July’2023
S.N | Station | Pt. No. | Date of Replacement |
1 | Amgaon | 41A | 16.07.23 |
2 | Gondia | 113A | 02.07.23 |
3 | Gondia | 419A | 16.07.23 |
4 | Gudma | 32A | 03.07.23 |
5 | Bortalao | 103A | 04.07.23 |
6 | Bortalao | 153A | 16.07.23 |
7 | Kachewani | 113A | 10.07.23 |
8 | Jatkanhar | 43B | 14.07.23 |
9 | Dongargarh | 110A | 15.07.23 |
10 | Gangajhiri | 103A | 16.07.23 |
11 | Tumsar Road | 104A | 16.07.23 |
12 | Rewral | 151A | 26.07.23 |
13 | Parmalkasa | 33B | 30.07.23 |
7.Wornout Point JB have been replaced at following stations in the month of July’23:
S.N | Station | Pt. No. | Date of Replacement |
1 | Birsola | 22B | 06.07.23 |
2 | Bhandara | 177B | 07.07.23 |
3 | Gudma | 152BT | 25.07.23 |
4 | | | |
8.Automatic Fire detection and Alarm system with Datalogger connectivity has been installed at
Samnapur station on 20.07.2023.
9.For improving reliability of track circuit, 31 nos. (As on 31.07.2023) of glued joints have been replaced in
association with Engg. Department in the month of July’2023.
10.Secondary cells have been replaced with new cells at the following stations in the month of
July23:
SN | Station | Nos. of batteries | Capacity |
1 | Samnapur | 03 | 80AH |
2 | Kamptee | 492 | 200AH |
3 | Gudma | 432 | 200 AH |
| Total | 927 | |
11.The New Internet /Railnet connectivity have been provided at following location in the month of July’2023.
i) Operating office/NGP -2 nos.
ii) Personnel/NGP-1 no.
12.The new voice logger LC Gate telephone have been installed in following non-interlocked LC gates of NGPDivision forthe month of July,2023.
i)LC gate no 68 (in between PTS-KPKD)
13.The OFC equipment along with all accessories & back up power supply arrangements have been shifted fromold OFC hut to new building OFC Hut at GDM on 13.07.2023.