IMPORTANT ACTIVITIES OF 2022-2023
Achievement and Highlights of S&T department, NGP Division for the month of
Dec-2022
Achievement and Highlights of S&T department, NGP Division for the month of Dec’2022 are given below for your kind perusal:-
1.Yard remodelling at Tarsa station (TAR) in connection with 3rd line between Rajnandgaon (RJN)- Kalumna (KAV)section has been commissioned on 24.12.2022 on A-route of Nagpur division of SECR by construction/NGP unit.
With this commissioning, Old Centralised Electronic interlocking with warm standby has been replaced with M/s Hitachi make Electronic Interlocking with Hot Standby (Distributed type) with MACLS system. After modification, no. of routes at Tarsa station has been increased to 90 nos. which were earlier 34 nos.
2.To improve reliability of point operation, old worn-out point machines have been replaced at following station in Dec’2022:
S.N | Station | Pt. | Date of Replacement |
1 | Parmalkasa | 33A | 03.12.2022 |
2 | Parmalkasa | 42A | 05.12.2022 |
3 | Rajnandgaon | 38B | 13.12.2022 |
4 | Itwari | 63A | 17.12.2022 |
5 | Rajnandgaon | 34B | 23.12.2022 |
6 | Parmalkasa | 41A | 23.12.2022 |
7 | Kalumna | 62B | 27.12.2022 |
8 | Rewral | 103A (insertion) | 28.12.2022 |
3.Wornout Ground connection has been replaced at following stations in the month of Dec’22:
S.N | Station | Pt. No. | Date of Replacement |
1 | Parmalkasa | 41A | 23.12.2022 |
2 | Parmalkasa | 42A | 05.12.2022 |
3 | Bhandara | 177A | 26.12.2022 |
4 | Kalumna | 62B | 27.12.2022 |
4.Old IPS battery set has been replaced with new battery set at the following station in the month of Dec’2022:
SN | Station | Nos. of batteries | Capacity |
1 | Birsola | 55 | 200AH |
5.Secondary cells has been replaced with new cells at the following stations in the month of Dec’2022:
SN | Station | Nos. of batteries | Capacity |
1 | Gonglee | 01 | 80AH |
2 | Tumsar Road | 03 | 80AH |
3 | Kamptee | 06 | 80AH |
4 | Kanhan | 03 | 80AH |
5 | Hirdamali | 03 | 80AH |
6 | Gudma | 02 | 80AH |
7 | Gondia | 03 | 80AH |
8 | Chacher | 06 | 80AH |
9 | Birsola | 03 | 80AH |
| TOTAL | 30 | |
6.For improving reliability of track circuit, 12 nos. of glued joints have been replaced in association with Engg. Department in the month of Dec’2022.
7.Battery for standby MSDAC 24V connected at Mid-section LC gate 492 between AGN-SKS on 07.12.2022.
8.Sliding barrier boom along with “four two ka one” circuit has been commissioned at the following interlocked LC gate to avoid train detention in case of dashing/failure of LC gate barriers:
S.No. | LC No. | Km no | Station/Section | Date of commissioning |
1 | TT-26 | 1077/12 | DGBZ Yard | 10.12.2022 |
9.The Mapple has been provided in the following section for arresting block failures (UFSBI & BPAC) on 22.12.2022.
i)PTS-SONR.
10.The New Internet /Railnet connectivity have been provided at following location in the month of December’2022.
i)Admin/ADRM(O) /NGP Office -02 nos.
ii)CMS/Polyclinic /MIB Office - 01 no.
iii)Work shop/MIB Office- 02 Nos
11.25 numbers of CGDB (Coach guidance display board) have been commissioned at BRD station P.F. no (1) on 22.12.2022.