Achivement in 2022-23 (Up to Nov’22)
1.Energisation of OHE at Bharvelly MOIL siding
OHE at Bharvelly MOIL siding taking off from Balaghat station from Mast location No. 1044/01, Ch. KM. 1044/01.20 to location no. 1049/21 (Ch. KM 1049/407.00 (total 6.397 TKM) charged on 13.05.2022 in Nagpur Division.
2. Charging of M/s Rita Steel Siding
OHE of private siding of M/s Rita Steel Industries Pvt. Ltd. Taking off from KNHN station yard with 4 nos. new X/Overs and extension of shunting neck (NGP end), new wiring at line no. 7 at KNHN yard (Total TKM :5.32) is charged on dtd. 22.09.2022.
3. Charging of NTPC Mouda Stage-II
NTPC Mouda Stage-II OHE work from reception yard to In plant Yard Stage II at reception yard and In plant yard Area is charged on dtd. 23.09.2022 (Total 11.067 TKM).
4. Successful completion of PCEE/SECR Inspection in TMR Rd- KWN 3rdline Section
PCEE/SECR Inspection for the electrification work of Tumsar Road (Excl.) (KM: 1049.315) to Kachewani (Incl.) (KM: 1021.600) (Total 28.00 RKM, 35.311 TKM) has been carried out successfully on 16.09.2022.
5. Successful completion of PCEE/SECR Inspection in PUE-BHV Section
During the month, PCEE/SECR Inspection for the electrification work in Palari (Excl.)-Bhoma (Incl.) (Total 20.47 RKM, 21.82 TKM) has been carried out successfully on 29.07.2022.
6. Enhancement of Contract Demand at RJN & PJB Traction sub station
During the month, enhancement of Contract demand for additional 2000 KVA (Over and above existing 16000 KVA) at Rajnandgaon TSS (18 MVA) & Contract Demand for addl. 2000 KVA (Over and above existing 22500 KVA) at Paniyajob TSS (24.50 MVA) has been done on 08.07.22 & 23.07.2022 respectively.
7. Energisation of DEMU Shed line no.2
OHE of line no.2 of DEMU Shed at Gondia for the maintenance of MEMU Rakes (total 0.560 TKM) charged on 27.07.2022.
8. Provision of PTFE type (Arthur Flurry AG make) Short NS Assembly at BRD/TSS & KWN/TSS:
Arthur Flurry AG make Short NS Assembly PTFE type has been provided at location no.1065/24 (DN Lin) (28.06.22) and 1065/23 (UP line) (04.07.22) in front of BRD TSS & 1022/18 (DN Lin) (31.08.22) and 1024/31 (UP line) (02.09.22) in front of KWN/TSS respectively.
9. Provision of Double contact Wire
Double contact wire provided at 26 locations of Sharp angle termination of OHE at in JBP-G section and KAV, RSM & RJN Yard for strengthening the OHE.
10. Replacement of Rusted Anti-creep Wire
Total 168 nos. rusted anti-creep has been rectified during the year. (Balance population as on date is 196 nos.)
11. Rectification of Leaning Mast
Total 63 nos. leaning mast has been rectified during the year. (Balance population as on date is 316 nos.)
12.Improvement of Critical Implantation
Total 8 nos. leaning mast has been rectified during the year.
13.LA Disconnector Switch shifting
102 nos. LA disconnector switches have been shifted on top of LAs during the year.
14.PTFE shifting at Balaghat SP
PTFE of BTC/SP provided in Balaghat-Katangi single line section has been shifted from loc.1044/31 to 1044/18 for interlocking of LC Gate to maintain the 400 mtrs. Clearance from Signal by Construction.
15.Charging of BHV/TSS
Bhoma/TSS with One 21.6/30.24 MVA Traction Transformer under CWA-NIR-MFR section charged on 25.08.2022.
16. Charging of Transformer TR-04 at PJB/TSS
At Paniyajob/TSS, One 21.6/30.24 MVA Traction Transformer, TR-04 (Make: CGL) has been charged and load given on 27.04.2022 (at 16:00 Hrs.).
17.Catenary Wire Replacement
Total 14.65 Kms. AAA catenary has been replaced by Cu Catenary wire during the year.
18.Charging of TRO/SSP
During the year, New TRO/SSP (KM. 1029/17-19) has been charged and shifted in connection with electrification work of 3rd line between RJN-NGP section on dtd. 09.07.2022 by Construction.
19.Charging of CHCR/SSP
During the year, OHE has been shifted on new CHCR/SSP & charged on dtd. 26.08.2022 by Construction department in connection with electrification work of 3rdline between RJN-NGP section
20.Charging of KP/SSP
During the year, OHE has been shifted on new KP/SSP & charged on dtd. 30.05.2022 by Construction department in connection with electrification work of 3rdline between RJN-NGP section
21.Charging of BAKAL/SSP
During the month, OHE has been shifted on new BAKAL/SSP (KM. 907/3-5), & charged on dtd. 19.11.2022 by Construction department in connection with electrification work of 3rd line between RJN-PJB section.
22.Charging of MUA/SP & DGG/SSP
During the month, OHE has been shifted on new MUA/SP (KM. 917/1-3) & DGG/SSP (KM. 926/28A-30A) by Elect./Con/NGP & charged on dtd. 25.11.2022 in connection with electrification work of 3rd line between RJN-NGP section.
23. Shifting of IOL at Signal Locations
4 nos. IOL in front of Signal locations partially shifted on temporary basis at SKY, GGGS, PNJ & HTT by adjusting height & droppers to avoid breakdown.
24. Provision Ashida make RTUs in place of M/s. Merit (V-Bro) make
At all 6 TSSs between DUG-NGP main line section, All RTUs have been updated from Ashida make RTUs (with latest RDSO’s spec.) in place of M/s. Merit (V-Bro) make, now EMS data is transmitting to SLDC/Kalwa & SEMC/BSP for power scheduling & forecasting under Open access.
25. Provision of ATs at BK-2 & GCF-2
10 KVA ATs for interlocking of LC gates no. BK-2 & GCF-2 have been provided departmentally.
26. Removal of Infringement at PF-2 of BRD Stn.
Portals has been shifted at PF-2 of BRD Stn. for the construction of the FOB’s stair, which was infringing the work.
27. Provision of Isolators for Improving Goods Shed
In order to provide Isolation facility for improving of Goods Shed, Isolators with earthing heal has been provided at MME (Work departmentally) and PNJ, HTT & BUQ Stations.
28.Provision of Double Contact wire under OLS
For strengthening of OHE under OLS, double contact wire provided at 21 locations under OLS
29. Isolation Facility at KPKD
Isolation facility has been developed at KPKD yard by provision 9-T Insulators.
30. Launching/De-launching of Girders
In order to launch the Girders of FOB at TMR, GNL & KPKD Stations, OHE slewing/Re-slewing has been carried out to facilitate the crane working. Similarly for de-launching of Girders at SKS & AGN stations OHE slewing/Re-slewing has been carried out to facilitate crane working.
31. Slewing/Re-slewing of OHE
For LHS Girder launching in the TRO-MNU in both UP & DN lines & KNHN-KP section in DN line, Slewing/Re-slewing of OHE has been done to facilitate crane working