Major Achievement of S&T department ( Year 2020-21)

******************************************************************************

April’20

 

1)To enhance reliability, followingworn out point machine has been replaced with new one in April-20:

S.N

Station

Pt. No.

Date of Replacement

1

Tharsa

33A

12.4.2020

 

 

 

 

2)Track circuit battery cellshavebeen replaced at the followingstations by new one in April-20 :-

S.No.

Station

Nos.

S.No.

Station

Nos.

1

Aamgaon

1

4

Kanhan

3

2

Darekasa

6

5

Rajanandgaon

3

3

Gondia

18

6

Kalumna

6

 

 

 

 

 

 

3)To improve reliability of point operation, old worn-out Ground connection of point machine has been replaced in coordination with Engg. Department at following station in April-20:

 

S.N.

Station

Pt. No.

Date of Replacement

1

Gondia

401A

15.4.2020

 

4)Wornout Tounge rails have been replaced in coordination with Engg. Department at following stations :

 

S.N

Station

Pt. No.

Date of Replacement

1

Gondia

429 B

10.04.20

2

Bhandara

33A

24.04.20

 

 

 

5)Signal cable maggering has been conducted at 28 numbers (AGN, BAKL, BRD, BTL, CHCR, DKS, DGG, GJ, G, GNL, ITR, KAV, KP, KNHN, K, MUP, NAB, PJB, RJN, RSM, SKS, SAL,TAR,TMR, SNV, PDE, DKU & GNS ) of stations in April-20.

 

6)6-Quad cable maggering has been conducted at 18 sections (RRL-TAR, KNHN-SAL, MNU-TMR, TAR-CHCR, KT-BRD, GJ-KWN, KWN-TRO, DGG-IBH, PJB-IBH, KT-RRL, TRO-MNU,TMR-K, KAV-NGP, BRD-K, BAKL-MUA, GJ-G, BAKL-RJN, RSM-MUP)on A route in April-20.

 

7)For improving reliability of track circuit 06 nos. of Glued joints have been replaced in association with Engg. Department.

 

8)All S&T(open line) employees of NGP Division have been provided with Face masks (approx.1000 nos.) and hand sanitizers,Hand wash as well as Soaps to maintain cleanliness and safeguarding against COVID-19.

 

May’20

 

9)To improve reliability of point operation, old worn-out point machine has been replaced at following station in May-2020:-

 

S.N.

Station

Pt. No.

Date of Replacement

1

BRD

43A

19.05.2020

2

PJB

5B

30.05.2020

 

10)For improving reliability of track circuit 10 nos. of glued joints have been replaced in association with Engg. Department in the month of May-2020.

 

11)Signal cable meggering has been conducted at 11 numbers (CWA, LIG, BMC, RMO, ULA, BDKD, MNU, G, AGN, GDM & SKS) of stations in the month of May’2020.

 

12)One day Safety seminar has been conducted at chhindwara on “Fail Safe adjustment of track circuit and Pre monsoon precaution”on 20.05.20 which was attended by 7 staff.

 

13)Track circuit battery cellshavebeen replaced at the followingstations by new one in the month of May’2020 :-

S.No.

Station

Nos.

S.No.

Station

Nos.

1

Kamptee

6

4

DGG

2

2

Gondia

15

5

BTL

1

3

Rajnandgaon

1

6

KAV

1

 

 

 

 

 

 

14)Earth testing work have been done at 47 number stations: Rasmara, Murhipar, Rajnandgaon, Bakal, Musra, Jatkanhar, Salekasa, Amgaon, Gudma, Gangahjiri, Kachewani, Tirora, Mundikota, Koka, Khat, Rewral, Tharsa, Chacher, Kalumna, Itwari, Khaperkheda, Patansaongi, Saoner, Kelod, Ramakona, Bhimalgondi, Bhandarkund, Umranala, Linga, Birsola, Hatta, Balaghat, Katangi, Waraseoni, Samnapur, Nagbhir, Talodhi, Chanda fort, Garah, Gowarighat, Burgi, Sukrimangela, Sikara, Ghunsore, Pindrai, Nainpur, Chiraidongri, stationsin May’2020.

 

15)Fuse alarm system wiring with data logger done at 3 stations (KP, KNHN & SAL).

16)Directed maintenance conducted at 4 stations BAKL, BTL, KAV and TRO.

 

17)Safety integrity test has been completed at AJU station on 25.5.2020.

 

18)The battery backup of OFC equipment of the following station has been changed in the G-CAF section:

Sr. No.

Station

Battery Make/Capacity

Nos

Date

1

SYE

LABCO/120AH

24

19.05.2020

 

19)The earth testing of following 62 Nos. stations for Telecom gear of Nagpur divisionhas been conducted in the month of May’2020.

ITR, KAV, KP, KNHN, SAL, CHCR, TAR, RRL, KT, BRD, TMR, MNU, TRO, KWN, GJ, G, GDM, AGN , DNL, SKS, DKS, BTL, PJB, DGG, JTR, MUA, BAKL, RJN, PMS, MUP, RSM, GBRI, DGBZ, TRDI, CID, NIR, PDE, NDNI, GNS, VNK, SKY, SNV, WSA, BMP, NAB, TUD, AWH, SYE, ROL, MME, KEZ, CAF, BRA, HTT, BTC, WRI, KGE, BDKD, ULA, LIG, DKU & RTK. 6-Quad cable meggering has been conducted at RRL-KT section in may-2020.

 

 

 

 

June’20

 

20)As part of Disaster management plan, “Temporary control office” has been set up in the conference hall at 3rd floor at CE/Construction office/NGP along with the following facilities:-

 

I.Three control Board.

II.FOIS terminal.

III.COA terminal link

IV.ICMS terminal link.

 

21)Modification of LC gate circuit and associated Automatic signaling circuit have been done departmentally due to closer of interlocked LC gate no. 566 between KAV-KP section during commissioning of LHS on 22.06.2020.

 

22)To check the healthiness of IPS batteries, “battery sustainability test” has been conductedat all stations of NGP Division in June’2020.

 

23)Signal cable insulation testing has been conducted at three numbers (GGGS, PMS& JTR) of stations in the month of June’2020.

 

24)Pre monsoon precaution Drive has been conducted at all the stations of Nagpur Division in June’2020.

 

25)For improving reliability of track circuit, 8 nos. of Glued joints have been replaced in association with Engg. Department in the month of June’2020.

26)Fuse alarm panel has been connected to datalogger and online validation has been completed in 11 nos. of Automatic signaling/ LC gate goomties (487, 488, 489, 490, 491, 492, 493, 494, 498, 499 and 500) in the month ofJune’2020.

27)The SCADA operation of TSS at Kachewani has been connected through Railway 2Mbps link on 22.06.2020.

 

28)New Railnet/Internet connectivity have been provided in following locations of Nagpur division in the month of June’ 2020.

i)Track machine office/MIB- 03 nos.

ii)Personnel /NGP-------------- 01 no.

iii)Elect(OP)/NGP--------------- 01 no.





 





Source : South East Central Railway CMS Team Last Reviewed on: 03-08-2020  


  Railnet Mail Login | Admin Login | Site Map | Contact Us | RTI | Disclaimer | Terms & Conditions | Privacy Policy Valid CSS! Valid XHTML 1.0 Strict

© 2016  All Rights Reserved.

This is the Portal of Indian Railways, developed with an objective to enable a single window access to information and services being provided by the various Indian Railways entities. The content in this Portal is the result of a collaborative effort of various Indian Railways Entities and Departments Maintained by CRIS, Ministry of Railways, Government of India.