1 | In order to ensure uninterrupted safe running of traffic Track renewals are planned to the extent of 18.24 Kms . |
2 | Replacement of track fittings which are outlived during the course of running i.e. Through fittings renewals completed during last year 173 Kms and planned 220 Kms during 2015-16. |
3 | Turnout renewals are planned to the extent of 92 Nos. |
4 | Ballast supply110000 cum |
5 | Installation of water level measuring system planned on 4 important bridges first time in the division. |
6 | Raising of sectional speed planned in Balaghat - Katangi section. |
7 | Removal of permanent speed restrictions planned at 2 locations in Itwari yard. |
| Passenger Related works |
1 | In order to provide improved facilities to the passengers followingworks are executed by the division under Touch and Feel scheme. |
| a) Moderanisation of stationsdone at RJN, DGG, AGN, G, TMR, BRD, KP, WSA, CWA, SEY, BTC, NAB, SNV CAF, MFR |
| b) Development of Adarsh Stations developed at Chhindwara, Itwari.Planned in 2015-16 at Howbagh, Gondia & Bhandara Road |
| c) Extension of Platforms to accommodation completed in previous years at DGG, BRD, AGN, KP, CAF. Planned during 2015-16at Kalumna, Birsola &Waraseoni |
| d) Development of circulating areas at RJN, DGG, AGN, G South & North side, TMR, BRD, KP, CWA. |
| e) Raising of platform work at Ramtek‘B’ category station has been completed |
| f)Improvement of platform surface at RJN, DGG, DKS, SKS, G, TMR, BRD, KP |
| g) Extension/provision of FOBs planned atRajnandgaon & Darekasa |
| h) Provision of small platform shelters planned to the extent of 24 Nos. in 2015-16. |
| i)Provision of Water Recycling Plant planned at Gondia in 2015-16 |
| j) Provision of minimum Essential Amenities planned at 44 stations. |
| k) |
2 | Following Facilities for physically challenged persons are also undertaken at 5 Stations at Rajnandgaon, Gondia ,Bhandara, Itwari & Chandafort. |
| a)Provision of separate toilets for physically challenged persons in 'A'& 'B' category stations. |
| b)Provision of Taps on platforms |
| c)Provision of separate parking slot |
| d)Provision of non slippery path way from parking slot to Station buildings. |
| In order to improve ground level water following RWH works done in the division |
1 | Rain water harvesting done at Mushra, Dongargarh, Gudma, Gondia, Tumsar Road, Bhandara Road, KachewaniNagpur, Chhindwara, Kamptee, Kanha rest house, Saoner Type-III qtr. |
2 | Planning done for provision of Rain Water Harvesting at 14 No. of locations during 2015-16 |