SAFETY ACTION PLAN FOR 2020-21 |
S.No. | Item | Unit | Target for 2020-21 | Prop Target Feb'2021 | Progress Till Feb'2021 |
1 | Accident on S&T account | | | | |
| (a) No. of accidents due to Equipment failure | Nos | 0 | 0 | 0 |
| (b) No. of accidents due to Human failure | Nos | 0 | 0 | 0 |
2 | Failure of equipment on unsafe side | Nos | 0 | 0 | 0 |
3 | Safety Inspection by S&T officials | | | | |
| (a) Safety inspection atSectional Inspector level (Monthly) | Nos | 636 | 583 | 528 |
| (b) Safety inspection atIncharge Inspector level(Quarterly). | Nos | 212 | 194 | 176 |
| (c)Safety inspection atASTE, DSTE, Sr.DSTE’s level (Yearly) | Nos | 51 | 47 | 110 |
4 | Joint Inspection of S&T officials | | | | |
| (a) Foot plate inspection by CSI/CL.I & CDTI (Quarterly) | Nos | 32 | 29 | 27 |
| (b) Points & Crossings by CSI/PWI | Nos | 177 | 162 | 156 |
5 | Training of safety category staff (Refresher) | | | | |
| (a) Signal Supervisors ( Once in 5 years ) | Nos | 1 | 1 | 15 |
| (b) Telecom. Supervisors ( Once in 5 years ) | Nos | 1 | 1 | 6 |
| (c) Signal Maintainers ( Once in 5 years ) | Nos | 8 | 7 | 18 |
| (d) Telecom. Maintainers ( Once in 5 years ) | Nos | 2 | 2 | 6 |
| (e) Safety Seminar (2 Nos.per month.Divn.) | Nos | 20 | 18 | 10 |
6 | Periodical Medical examination of safety category staff | Nos | 8 | 7 | 11 |
7 | Overhauling of Signalling equipment | | | | 0 |
| a) Lever frame ( Once in 3 years ) | Nos | 4 | 4 | 0 |
| b) Block instrument (DLBI-once in 7yrs & SLBI/TLBI-once in 10 years) | Nos | 9 | 8 | 9 |
| c) Shelf type relay Track(Once in 12 years) | Nos | 0 | 0 | 0 |
| d) Shelf type relay Line(Once in 15 years) | Nos | 0 | 0 | 0 |
| e) Cable meggering | Nos | 33 | 30 | 35 |
8 | System Integrity Test | Nos | 2 | 2 | 24 |
9 | Sign off Register - Compliance of defficiencies reported | Nos | 0 | 0 | 0 |
10 | Maintenance of VHF communication (for Gd/Driver): | | | | |
| a) Replacement/repair of defectivesets. | Nos | 100 | 92 | 120 |
| b) Replacement/repair of defective battery chargers. | Nos | 50 | 46 | 24 |
| c) Replacement of battery (Once in a year) | Nos | 10 | 9 | 150 |
11 | Joint checking of emergency sockets (Quarterly by SE/Tele & SSE/OHE) | Nos | 1000 | 917 | 652 |
12 | Inspection of ART & ARME equipments | | | | |
| (a) Inspection at JE/SSE level (Monthly). | Nos | 15 | 14 | 10 |
| (b) Inspection at Officer level (Quarterly) | Nos | 4 | 4 | 6 |
13 | Inspection & testing of assets for Disaster Management | | | | |
| (a) Inspection at JE/SSE level (Monthly). | Nos | 15 | 14 | 10 |
| (b) Inspection at Officer level (Quarterly) | Nos | 4 | 4 | 6 |
14 | Provision of shortfall safety materials in ART/ARME. | | | | |
a | Provision of one more satellite phone at all ARTs | Nos | All ready provided | -- | 0 |
b | Provision of System showing the coverage availability of measure mobile service provider in ART | Nos | All ready provided | | 0 |