VISION AND ACTION PLAN:
“Our vision is to ensure un-interrupted power supply to Electric Traction for running of Trains with safety & punctuality”
ACTION PLAN:
Maintenance of Asset: Targets and Progress
SN | Item | Target 14-15 | Prop. Target 14-15 (Apr-Dec) | Actual 14-15 (Apr-Dec) |
OHE |
1 | IOH of OHE (TKM) | 354 | 265.5 | 149.346 |
2 | POH of OHE (TKM) | 170 | 127.5 | 33.529 |
3 | POH of ATD | 451 | 338 | 160 |
4 | Checking of Turn Out | 372 | 279 | 51 |
5 | Checking of Cross Over | 245 | 184 | 46 |
6 | AOH of Isolators (OHE) | 281 | 211 | 75 |
PSI |
1 | AOH of Transformer | 205 | 150 | 112 |
2 | AOH of Interrupter | 121 | 91 | 98 |
3 | AOH of CBs | 28 | 21 | 28 |
4 | AOH of Isolator (PSI) | 179 | 129 | 56 |
5 | Maintenance of Gantry | 19 | 14 | 5 |