ENGINEERING
Progress of 10 important activities
Sl. | Item | Target | Pro rata | Progress |
No. | | | target upto | upto |
| | | Nov.-17 | Nov.-17 |
1 | CTR (In CTR units) | 72.50 | 48.33 | 37.53 |
| | | | |
2 | Deep Screening (KM) | 213.5 | 142.3 | 62.06 |
| | | | |
3 | TTR (Nos.) | 136 | 90.67 | 63.00 |
| | | | |
4 | Greasing of ERC | 480 | 320 | 238.09 |
| | | | |
5 | Output of USFD (KM) | 3750 | 2500 | 2628.04 |
| | | | |
6 | Scrap Offered to stores (MT) | 4000 | 2667 | 3006.30 |
| | | | |
7 | Toe load measurement (KM) | 147 | 98 | 41.68 |
| | | | |
8 | Construction of Rainwater harvesting |
|
|
|
| structures(No of stations) | 6 | 4 | 2 |
| | | | |
9 | Earning through Unconventional Sources (Crores) | 13 | 9 | 8.73 |
|
| | | |
10 | Drawn of completion report(No of cases) | NR | NR | 57 |
| | | | |
Highlights of the Month:-
1.01 Overall mobility index of the division is 88.
1.02100 Nos. hard encroachments has been removed from Dhamtari station area on
21.11.17 with the help of RPF & Local State authority.
1.03New Pipe line connection for new pump house at Kharun river pump house
completed.
1.04 Replacement of 350 mtr. C.I. Pipe line with D.I. Pipe line has been completed from Br.No.11/C to 11/D at BMY. Total 2200 mtr. has been replaced upto the month.
1.05 650 mtr. G.I.Pipe line repaired at BIA & PP Yard colony during this month.
1.06 Replacement of damaged AC Sheet with Galvalume sheet of BOBY I shop in bay number EL/96 & EL/97 WRS at height of 40’ with taking extra safety measures.
1.07 During the month 5.25 TKm TWR has been done in DN line BSP-NPI section by MFBWP. Total 21.95 TKm TWR has been done by MFBWP upto the month. Total 3300 AT welds have been removed by 3385 FB welds including 1729 defective welds removal. All the SEJs & GJs coming in TWR patches has been renewed & welded by FB welds for more safety & better running.
1.08 Gradient correction work done at Reception yard BMY in UP Reception line 1,2,3 & DN Reception line 1,2,3 towards Raipur end to avoid chances of rolling down.
1.09 160 mtr. boundary wall constructed during the month. Total 2246 mtr. boundary wall constructed upto the month against proportanate target of 1733 mtr.
1.10 37.50 TKm. dressing & boxing has been done during month. Total 246.13Tkm. has been done up to the month.
1.11 7.95 Tkm. CTR has been done during month. Total 37.53 Tkm. CTR has been done up to the month.
1.12 Overhauling ofLevel crossings19 of BGsectionhas beendone. Total overhauling of 87 LCs has been done up to month against proportanate target of 37LCs.
1.13 Overhauling of 20.86TKm. Track &20 T/Outs has been done during month.
1.14 126 Nos. Overhead tanks have been cleaned of BYT, TLD, DRZ, BMY,Engg. Colony& WRS colony Raipur.
1.15 41Qtrs. Leaky roofs repairs has been done during month. Total 721Qtrs. Leaky roofs has been repaired upto the month against proportanate target of 265Qtrs.
1.16 27 Qtrs. Identified based on survey has been repaired during month. Total 204 Qtrs. has been repaired upto the month against proportanate target of 100 Qtrs.
1.17 676425
sqmtr. Vegetation& Jungle cleaning has been done at CHBT, DGS, BYT, TLD, BKTH, MDH, DUG, BXA, DRZ, BMY, ENGG, RVH & WRS colony during month.
1.18 290 mtr.drains repaired/improved in SLH& WRS Yard and 150mtr. atSLH, DRZ, RVH& WRS colonyduring month.
1.19 06 Nos. outstanding final bills&10Nos. live contracts bills has been cleared during month. Total 91 final bills& 84 live contracts bills has been cleared upto the month.
1.20 05 Nos. CR (Completion Report) has been drawn this month.
<!--[if !supportLists]-->2.<!--[endif]-->Highest ever achievement (indicating previous best in the last 5 years) –
SN | Item or Work | Unit | Performance | Month and year of Previous best | Remarks |
Achieved Now | Previous best |
1. | NIL | - | - | - | - | |