HIGH SPEED 130/160 KMPH
For rising of speed following OHE modification/up gradation work is involved;
Issues to be ensured | Qty | Progress |
Provision of BFB steady arm (RI no. 2390) with 25 mm drop bracket assembly (RI no. 2360) at every cantilever of OHE on main line | 35 locations | 18 have been provided. TDC- Sep’15 |
Removal of cross type OHE between BTL yard. | 1 location | Work completed. |
Removal ofSection Insulator frommain line | 05 locations | 01 no. section insulator removed from Main line in Gondia yard.TDC – Sep’15 |
Provision ofPTFE at Paniajob TSS | 1 location | Work completed. |
Provision of 3rd bay at Paniajob TSS | 1 location | Work proposed in PWP 2015-16. |
MISSION 160+ WORKS: Progress of Mission 160+ items is summarized below:
Sr. No. | Name of work | Executing Agency | Status/ Progress |
1 | Electrification of OHE modification in Chacher Yard for NTPC project (2*500) at mouda.Phase-I | RITES | Completed |
2 | Electrification of OHE modification in Chacher Yard for NTPC project (2*500) at mouda.Phase-II | RITES | Work is held up due to incomplete track work laying of loop lines. |
3 | Expansion Project (3x660MW) at Koradi TPS for M/s MSPGCL | RITES | 2.40 TKM work completed. |
4 | Thermal Power Station Expansion Project at Khaperkheda for M/s MSPGCL | RITES | Total 15.692 TKM OHE charged. Balance work in progress. |
5 | Gondia Yard - Crossover at Nagpur end to connect Chanda Fort grid | DRM/NGP | LOA issued. OHE LOP under finalisation. |
6 | Provision of over run line on goods shed line and increasing CSL of line No.8 at Gondia | DRM/NGP |
HUMAN RESOURCE DEVELOPMENT:
To improve the skills of TRD staff & supervisors every month training programme is prepared & staff is deputed to participate in different training institutes of Railways such as AICTC/CKP, CETE/THK, STS (Tower wagon) /KGP, ZRTI/SINI, MDTC (Multi Disciplinary Training Center)/BSP etc. In year 2015-16 (up to July’15) we have given training to 24 nos. of staff.
Sr. No. | Training Centre | Courses | No. of staff Attended training in the Year 2015-16 (Up to July '15) |
Super-visor | Tech-nician | T/W & M/V Driver | Group 'D' |
1 | AICTC, CKP | Initial course | -- | -- | -- | 5 |
Refresher Course | -- | 5 | -- | 3 |
2 | MDTC/BSP | Refresher Course | -- | 10 | -- | -- |
3 | Sini/Uslapur | Refresher | -- | -- | 1 | -- |
Total No. of staff attended | 0 | 15 | 1 | 8 |