ENGINEERING

Progress of 10 important activities

Sl.

Item

Target

Pro rata

Progress

No.

target upto

upto

June-17

June-17

1

CTR (In CTR units)

 

72.50

18.13

7.83

2

Deep Screening (KM)

213.5

53.38

26.58

3

TTR (Nos.)

136

34.00

22.75

4

Greasing of ERC

480

120.00

88.92

5

Output of USFD (KM)

3750

938

          936.49

6

Scrap Offered to stores (MT)

4000

1000

1635.55

7

Toe load measurement (KM)

 147

36.75

13

8

Construction  of  Rainwater  harvesting




structures(No of stations)

         6            2           1

9

Earning through Unconventional Sources (Crores)

13

3

0.37


10

Drawn of completion report(No of cases)

NR

NR

30


Highlights of the Month:-

1.01. Overall mobility index of the division is 103.

1.02.Jacketing of important Br.No.462 DN in between DGS-NPI section has been completed.

1.03.Escalator on PF No. 1 at Durg has been completed and with it Durg station has become Adarsh Station as per Railway Board guideline.

1.04.19 bay New PF shed provided on PF No. 2/3 of Durg station.

1.05.A Divisional level seminar on “Monsoon Precautions” has been organized on 09.06.17 at Divisional conference hall, Raipur.        

1.06.TFR of steel channel sleepers of Br.No. 462 UP/DN/MID & Br.No. 478 DN/MID has been completed.

1.07.300 mtr. chain link fencing has been completed during month. Total 1400 mtr. has been completed at RVH colony, Raipur.

1.08.230 mtr. boundary wall constructed under integrated security system at Raipur station & 220 mtr. at BMY along the NH.

1.09.Replacement of CI pipe line with DI for Sirsa Filter House at BMY has been completed & Additional work for repairs to CI pipe line with DI is in progress for Zone I Filter House. (Total = 1850 mtr)

1.10.27 Nos. damaged AC sheet of BOBY II Shop, WRS has been replaced with galvanized sheet.

1.11.Renewal of rusted/corroded lead rails & Check rails at Raipur Pt.No. 59A, 53A, 54 & Urkura Pt.No. 64A, 67A has been done.

1.12.12.30 TKm. dressing & boxing has been done.

1.13.3.41 Tkm. CTR has been done.

1.14.Deep screening of 04 Nos. of points & Crossings has been done manually at MNDH & BMY.

1.15.Deep screening of 6.09 TKm has been done by BCM.

1.16.02 T/O (1in8.5) TTR at BMY & 01 D/S (1in8.5) at KMI has been done manually.

1.17.Overhauling of Level crossings 06 of BG & 06 of NG section has been done. Total overhauling of 34 LCs has been done up to month.

1.18.Overhauling of 0.29 TKm. & 02 Pts/Xings has been done manually.

1.19.201 Nos. Over head tanks have been cleaned of BYT, TLD, BMY & WRS colony Raipur.

1.20.67 Qtrs. Leaky roofs repairs has been done.

1.21.20 Qtrs. Identified based on survey has been repaired during month.

1.22.4,25,500 sqmtr. Vegetation & Jungle cleaning has been done at BYT, BIA, DUG, BMY, ENGG., RVH & WRS colony.

1.23.1235 mtr. drains repaired/improved in SLH, DRZ, BMY Yards & WRS workshop and 5157 mtr. at BYT, BIA, BMY & WRS colony as a Monsoon precautions.

1.24.0.058 Tkm. corroded/wheel burnt rail renewed.

1.25.1191.64 MT scrap has been offered during this month.

1.26.06 Nos. outstanding final bills & 08 Nos. live contracts bills has been cleared.

1.27.09 Nos. CR (Completion Report) has been drawn this month.

2.Highest ever achievement (indicating previous best in the last 5 years) –

SN

Item or Work

Unit

Performance

Month and year of Previous best

Remarks

Achieved Now

Previous best

1.

NIL

-

-

-

-

-




Source : South East Central Railway CMS Team Last Reviewed on: 10-07-2017  


  Railnet Mail Login | Admin Login | Site Map | Contact Us | RTI | Disclaimer | Terms & Conditions | Privacy Policy Valid CSS! Valid XHTML 1.0 Strict

© 2016  All Rights Reserved.

This is the Portal of Indian Railways, developed with an objective to enable a single window access to information and services being provided by the various Indian Railways entities. The content in this Portal is the result of a collaborative effort of various Indian Railways Entities and Departments Maintained by CRIS, Ministry of Railways, Government of India.