SUB:- :- M.C.D.O. FOR THE MONTH OF JUNE-2015

 

1.0

ACHIEVEMENTS DURING THE MONTH

 

1.1

A Normal height subway at Tarbahar levelCrossing in Bilaspur Yard. 9 Nos of tracks with 92 m Box lengthwith approach covering has been commissioned during the month

 

1.2

Four no normal height subways (At manned LC CI-45 KM 1319/7-8) , U/M LC CI-48 KM 1323/4-5, U/M LC CI-101 KM 1382/8-9& U/M LC CI-102 KM 1383/5-6) between Chhindwara-Nagpur completed & opened to road traffic during the month.

 

1.3

Two Minor bridges (Br.No.416&317A) between Jabalpur- Nainpur completed during the month

1.4

1.31 Lakh cum earth work (0.59 Lakh cum between Jabalpur-Nainpur & 0.72 Lakh cum between Chhindwara-Nagpur ) completed during the month. .

1.5

At Saoner, 3.99 hect land was required for circulating area of new station building as per approved yard plan. By relocating the proposed station building by 54.0 m towards CWA end from existing station building, the requirement of additional land acquisition has been avoided

1.6

Casting of 10 Nos PSC girders of Major Bridges between Champa-Kharsia has been completed .

 

 

 

2.0

EXPENDITURE

 

2.1

Expenditure during the month38.36Crores

2.2

Cumulative expenditure up to June. – 2015116.65Crores

 

Break up of expenditure under various Plan Heads is detailed as under

( Figures in Crores of)

 

 

 

No

Plan Head

Year 2014-15

Year 2015 -16

 

BG

14-15

FG

Exp. During June. 14

Exp. In 14-15 up to March-15

CAP/ DF

/DRF

 

 

Exp.

During

Month

Cum. Exp. up toJune.15

% age Exp. on Cap

1

New Lines

 

6.2

0.02

0

0.01

15.50

0

0

0

2

Gauge Conversion

220.1

210.36

15.55

212.27

429.90

17.18

73.43

17.08

3

Doubling/3rd line

176.7

150.56

7.85

145.85

309.60

14.72

29.60

9.56

4

Traffic facilities

 

28.8

31.31

0.1

20.34

64.00

1.31

3.40

5.31

5

Road Safety Works(ROB)

40.84

27.31

3.51

26.35

25.86

1.98

5.40

20.88

6

Bridge Works

 

0.05

0.26

0.02

0.27

0.20

0

0.00

0.00

7

Work Shops

23.97

26.82

2.03

19.56

30.78

1.5

2.60

8.45

8

Staff quarters

10.81

6.42

0.08

3.73

14.91

1.37

1.76

11.80

9

Amenities for staff

2.05

1.97

0

1.54

1.50

0.23

0.23

15.33

10

Passenger Amenities

1.24

0.12

0

0.06

0.00

0

0

0

11

Other specified works

0.7

1.00

0.09

0.64

3.24

0.07

0.23

7.10

 

Total

 

511.46

456.15

29.23

430.62

895.49

38.36

116.65

13.03

 

3.0

 

NEW LINES

 

Status of the Projectssanctioned on this Railway is detailed as under

3.1

Dallirajhara – Jagadalpur New Line (235Km)-The work was sanctioned in1995-96 at an abstract cost of Rs 880.69 Cr. ( Phase-I-216.38 Cr. Phase II-664.31 Cr.)

Detailed estimate of Phase-I from Dallirajhara to Rowghat (95Km) was sanctioned in 2009 at a costofRs 631.78 Cr. Detailed estimate submitted to Railway Board on 28.1.2015 for sanction. Phase –I, funded by SAIL and Phase –II funded byRailway , NMDC and CG Govt .C.G.Govt will provide Govt. Land free of cost. As per Board’s directive dated 11.03.08, the Dallirajhara – Rowghat (95 Km) Phase-1 has been transferred to RVNL for execution. Execution of Phase-II is enterested to IRCON

Railways has provided employment to 209 eligible land losers in Balod district and 11 eligible land losers in Kanker district. SAIL has planned to provide employment to 177 land losers (44 in Balod district & 133 in Kanker district). ITI training is being given by SAIL to 114 land losers (44 in Balod district & 70 in Kanker district). Lump-sum package isto be given to balance land losers

Details of land acquisition for phase-I (Dallirajhara – Rowghat)

(i)Private Land: - Requirement of302.29 Hect.has beenfully acquired. Additional requirement of2.88 hec.and khasaradetailsreceived from RVNL on 28.08.12 and 24.09.12 respectively and submitted to SDM/Dondi on 01.10.12.Final award published on 6.01.14. but villagers refusing to take compensation and insisting for employment first. State Govt suggested to provide LC at two location and ROB at one location to minimize no of land losers. Land requirement and consequently employment to land losers has beenreviewed & approved by Railway

 

 

(ii) Government Land- 49.92 Hect.-- fully acquired

(iii) SAIL Land---Fully acquired and handed over to RVNL

(iv)Forest Land-Total requirement is 259.54 Hect. Stage - II clearance (Final approval) has been received on 24.03.2011 from MOEF. Tree cutting is done by forest deptt. Tree cutting in Balod distt. completed while in Kanker distt. in progress. Tree cutting has beencompleted in 40 out of 137.40 hect.andis in progress in balance land

Revenue Forest Land- For 83.12 Hect. Stage - I clearance from MOEF received in April-10 stage II clearance from MOEF receivedon 12.5.14. Tree cutting permission is given byCollector/Kanker on date 11.07.2014

Details of land acquisition for phase-II (Rowghat-Jagdalpur 140Km)

Application and set of land plans & land schedule for acquisition of land between Rowghat to Jagdalpur, has been submitted to Collector/Jagdalpur and DFO/ Narayanpur in October 2010. Registration fee was paid on 12.11.12. The case was registered on 10.02.2014. The detailed estimate costing of Rs 1702 Crsubmitted to Railway Board on 28.1.2015

Progress of Phase-I-

(a)Earth work of 15.90 lakh cum completed (Out of total 51.0 lac Cum)

(b) Minor bridges (Total 186 nos.) –Progress.30.17%

(c) Major bridge (total 13 nos.)-Progress 6.68%

(d) Ballast 62680 cum complited out of 284874 cum

(e) Track linking-17Km out of 95 Km

3.2

Wadsa – Gadhchiroli (49.50 Km.)

The work is sanctioned in the year 2011-12 at an abstract cost of Rs. 232.40 Croreson 50:50 cost sharingwith State Government of Maharastra. Part detailed estimate of Wadsa Yard – Part – A (Rs.27.55Cr) and part detailed estimate for long lead items – Part – B (Rs.405.72Cr) wassent to Rly. Board for approval on 08.07.2014.As per advise of Railway Boardafter revision of L-section , deletion of one loop line each at Gadhchiroli & Armori & deleting cost of two proposed ROB’s across NH. Detailed estimate costing Rs 403.00Cr. duly vetted by finance & approved by GMhas been submitted to Railway Board on 17.04.2015

 

3.3

Raigarh (Mand Colliery) - Bhupdeopur (63 km)- Work executed by IRCON

The work was sanctioned in2013-14 at an abstract cost of Rs.379.08.(Railway Board’ letterno.2010/W-II/SECR/SY/33 dated 21.11.2014) The original sanctioned project is modified asKharsia- Gharghoda-Korichhapar-Dharamjaigarh including spur from Gharghoda to Donga Mauha of approximatly 104 Km atcost of Rs 1646.61 Cr.videletter dated 21.11.14.Land Acquisition Collector, Raigarh demandedRs 82.50Cr. for land acquisition.Chief Executive Officer(CERL)Chhattisgarh East Railway Limited depositeda ChequeofRs 82.50 Cr. with the Railway and amount paidto Collector/Raigarh on 4.2.2015. Kharsia-Dharamjaygarh with spur line (0-75 K.m).20E Notification published for 271.827 Hact. of Privet Land on 07.04.2014 (0-10Km.) on 16.12.2014(10-74Km.).

 

3.4

Gevra Road - Pendra Road (121.70 km)- . Work executed by IRCON

The work was sanctioned in2013-14 at anabstract cost of Rs.838.02 Cr. Land acquisition is in progress. 20A Notification for 129.62 Hect. published on 22.04.2015 for Bilaspur District and for 74.760 Hect. published on 16.04.2014 for Korba District

3.5

Barwadih - Chirimiri (182 km)- The work was sanctioned in2013-14 at anabstract cost of Rs. 1137 Cr. with remark. “Expenditure /commitments on this project will be made only after obtaining necessary approvals. For changing the name from Barwadih - Chirimiri to Barwadih- Ambikapur, a letter has been written to Railway Board by GM/SECR on 23.07.2014.Railway Board had been advised for granting permission for execution of the project on 28.07.2014

 

3.6

Raipur - Jharsuguda (310 km) :The work was sanctioned in2013-14 at an abstract cost of Rs. 2121 Cr. with. “Expenditure /commitments on this project will be made only after obtaining necessaryApprovals’' letter written to Railway Board for granting permission for execution of the project on28.07.2014

 

4.0

GAUGE CONVERSION PROJECTS

 

4.1

Gondia – Jabalpurincluding Balaghat - KatangiGauge Conversion (285Km

The work was sanctioned in1996-97 at anabstract cost of386..69 Cr. Detailed estimate was sanctioned in 2001 at ancost of Rs 511.855 Cr. 1st revised cost of Rs 1037.90 Cr.(24.9.10),2nd revised cost 1476.43Cr.under finance vetting.

 

4.1.1

Gondia-Balaghat section :-(42+7)

Gondia-Balaghat Section including MOIL Siding (42+7 Kms) was Commissioned on 06.09.2005

4.1.2

Balaghat- Katangi section:-

Balaghat - Katangi section (46.8 Km.) was opened on 23.02.10

4.1.3

Balaghat - Nainpur section ( 77 KM):-

Forest Land- Acquisition of 20.60 hect forest land has been completed in Mandla District..For acquisition of balance 75.977 hect forest landin Balaghat district, stage- I clearance received on 05.02.15. For stage-II clearance, a committee has been nominated by WIIF, Dehradun on 14.05.2015. The committee likely to visit the site in 3rd week of July’15.

Pvt Land ( 37.42 hect) & Govt, Land (10.98 hect) already acquired.

Earthwork between BTC-SMC section and at Nagarwara station is completed to the extent possible,

Minor bridges- Out of 80 minor bridges,8 bridges are completed in all respect,72 bridges are partially completed, 27 nos. to be done in mega block and 12 Nos after forest clearance.

Major bridges- Out of 16 minor bridges, 12 no has been completed., 03 no partly completed& one to taken up after getting forest clearance.

Progress-Nainpur-Jabalpur

(a)Earth work of 91.52 lakh cum completed out of 118.00 lakh Cum

(b) Minor bridges 105 completed out of 225 Nos.

©Major bridges 25 completed out of 36Nos

(d) Ballast 183966 cum completed out of 260000 cum.

(e) Track linking-9.7Km completed out of 113 Km.

4.1.4

Katangi-Tirodi New line (15 km )

Katangi – Tirodi New line (15.9 Km) was sanctioned as material modification to Gondia – Jabalpur Gauge Conversion work at a cost of `119.64 Cr on 1.06.2011.

Land - i)Forest land

Forest land of 18.694 hect. in Balaghatdistrict was submitted by Railwayon 20.05.13. the case file has been sent to PCCF/LM/Bhopalthrough CCF/Balghat on 28.02.15 for approval for Stage I clearence

ii)Private land:

Application for entire Pvt. Landof 45.02 Hect has been filed in the month of May'13. Aprox. 8 Cr. towards anticipated compensation for acquisition of 45.02 Ha. (Pvt. Land) has been demanded by Land acquisition Officer Balaghat in the month of November 2013. Which was raised to Rs. 32 Crores as per new rate. However since the time limit of one year from the date of initial filing of application lapsed, fresh applicationfor the entire 45.02 Hact. has been re filed with SDM/Katangi on 09.12.14 A demand note of Rs 13.93 cr has been received from SDO/Katangi toward payment for anticipatorycompensation on 29.04.15.The amount is deposited on 3.6.2015.

iii)Govt. land :

Gazette notification for transfer of Govt land of 7.3 Hect from Dist. Collector /BTC sent to commissioner/Jabalpur on 21.04.15

The tender for the execution of work will be called after the land is made available by State Government & Forest department

 

 

 

 

 

 

 

 

5.0

Chhindwara– NagpurGauge Conversion (150 Kms)

The work was sanctioned in2005-06 at an abstract cost383.79 Cr. Detailed estimate at a cost of Rs 663.66Cr. was sanctioned on 27.11.12.Ist revised estimate costing Rs 1085.10 Cr. has been submitted to Railway Board on 23.12.2014

((i) Acquisition of forest land and tree cutting by forest department has been completed. Pre-mega block earth work – 60.35 lakh cum, 22 Major Bridges (Sub structure) and 19 Nos (Super structure) and 52 minor bridges completed. Further, 04 Major Bridges and 03 Minor Bridges are in progress. Important tenders for the entire pre mega block works for CWA-NGP section have been awarded/under finalization.

ii) Major Bridges super structure (Steel Girder)-.All girders for 4 spans of 12.2 m and 52 spans of 18.30m are fabricated by CWES/MMR Central Railway and brought to site. 50 Nos girders of 18.3 m. 9 spans out of total 10 spans of 30.5 m girder have also been brought to site and launched. One span of 30.5m is yet to be received from Sabarmati Workshop. All 24 span of 45.73m girder (15 spans from CWES/MMR & 09 spans from Sabarmati Work Shop) brought to site.

.

It is proposed to plan mega block between Nagpur-Chhindwara section from Nov.2015

Progress-

(a)Earth work of 61.67 lakh cum completed out of 100.85 lakh Cum

(b) Minor bridges 202 completed out of 247 Nos.

©Major bridges 22 completed out of 26Nos

(d) Ballast 2.27 lakh cum completed out of 3.68 lakh cum.

(e) Track linking-7.60 Km completed out of 179 Km.

 

6.0

Chhindwara – Nainpur – Mandla Fort Gauge Conversion (182 Kms)

 

The work was sanctioned in2010-11 at an abstract cost of Rs.556.54 Cr. Detailed estimate costing Rs 737.72 Cr. has been sanctioned on 03.03.12.

 

Forest Land-Stage -I clearanceissued by MOEF/ Bhopal on 02/09/2013 for diversion of forest land of 3.974 hect. in Seoni district. For further processingRly paid the amount of Rs. 1.5 Crore on 29.4.2014. Compliance of conditions given along with Stage-I clearance have been sent by CCF/Seoni to PCCF/LM/Bhopal on 07.6.14 and4.10.14. Permission for cutting of trees and execution of work received from PCCF/Bhopal office through CCF/Seonion24.01.15. A demand for Rs. 0.95 lacks was received from DFO/South/Seoni on 25.03.15 toward cutting of trees in the forest portion and removalof the same. The said amount was deposited to DFO/South/Seoni on 18.04.15.Cutting of tee is in progress.

Private land Application filed for full requirement 54.95 Hect.In Mandla Dist.( Sec-11 issued for 9.783 hect) out of 11.896 hect. and for rest acquisition in advance stage in Seoni Distt. Sec-11 issued for 31.29 hect. out of 32.104 hect and acquisition is in advance stage for balance portion. In Chhindwara Distt for complete 16.92 hect. of private land sec-11 has been issued.

Government Land : Total requirement 27.927 hect. Formal transfer of land to be done by State Govt.Between Nainpur -Seoni section award for Govt. land 24.707 Hect. to be passed.(all the document of govt. land of Keolari tehsil & Seoni tehshil resubmitted to collector Seoni on date 29-04-2015)

Progress-

(a)Earth work of 9.68 lakh cum completed out of 77.86 lakh Cum

(b) Minor bridges 59 completed out of 287 Nos.

©Major bridges 4 completed out of 22Nos

(d) Ballast 0.84 lakh cum completed out of 4.10 lakh cum.

(e) Track linking-NIL.

 

 

7.0

Nagbhir-Nagpur (106 km)

 

The work was sanctioned in2013-14 at an abstract cost401Cr.with remarks that Expenditure /commitments on this project will be made only after obtaining necessary approvals Detailed estimate costing of Rs 708.11 Cr. has been submitted to Railway Board on 06.05.2015 which is awaiting sanction.

 

 

 

8.0

 

 

Bilaspur – Urkura (110 Km), (The work between Bhatapara-Urkurais under execution byRVNL)

The work was sanctioned in1997-98 at an abstract cost of 235.78 Cr. The work Bilaspur to Bhatapara (45 km) hasbeencommissioned in 2005-06 at a cost of Rs 289.40Cr.. Bhatapara – Hathbandh has been commissioned on 14.07.10,Hathbandh -Baikunth has been commissioned on28.12.11,Baikunth – Silyari has been commissioned on 14.5.14.Silyari-Urkura is in progress.TDC- Silyari-Mandhar -31.1.2016

Mandhar-Urkura- 31.1.2016given by RVNL

 

9.0

Salka Road-Khongsara patch doubling (26 km),

The work was sanctioned in2005-06. at an estimate cost of Rs 143.87 Cr. The work is being executed by RVNL.Physical progress is54% and work is likely to be completed byMar’16.

 

10.0

Khodri-Anuppur, withfly over at Bilaspur- (61.6 km),

The work was sanctioned in2006-07. Detailed estimate cost of Rs 387.54 Cr. Physical progress is 76% Jaithari -Chhulha-Anuppur section commissioned in 09.11.14

(i)Acquisition of 15.71 hec of Pvt land for rail Flyover at Bilaspur is held upneedsto be expedited by State Govt

(ii) Stage II Clearance of forest land between Khodri-Sarbahara and Pendra –Harri section awaited from MOEF. 26.891 hectare of protected forest land is to be diverted in this connection as directed by DFO/Marwahi/Pendra. Railway have deposited of Rs 43546281/ on 26.11.2013.Further, on the direction of DFO/Marwahi/Pendra, Railway have additional deposited of Rs 38,42,208/- on 10.01.2014 towards the compensatory afforestation. Then, the DFO/Marwahi/Pendra has forwarded the proposal onwards to CF/Bilaspur circle/Bilaspur with a copy to CCF/LM/Raipur on 19.03.2014. Further vide letter dated 19.08.2014 demanded additional amount of Rs 2213784 due to increasing 10% labour charges, additional amountof Rs 22,13,784 has been deposited on 26.09.2014. Forest department vide letter No. 115-110/5040/ Raipur dated 6.6.15 have given permission for cutting the trees in 26.891 Hact. Protected forest land

TDC

i)-Anuppur-Chulha-Jaithari : commissioned

(ii)- Jaithari-Nigaura -TDC Nov’15

(iii)- Nigaura Venkatnagar –TDC Nov’15

(iv)- Venkatnagar-Harri -TDC Nov’15

(v)- Harri-Pendra Road -TDCMay 2016

(vi)- Khodri-Sarbahara- TDCMay 2016)

 

.

11.0

Raipur-Titlagarh doubling (203km). This work is being executed by E Co Rly.

(i) MM-I new line Mandirhasaud-Naya Raipur(20Km)

(ii) MM-II Gauge Conversion of Raipur(Kendri)-Dhamtari & Abhanpur—Rajim branch (67.20Km)

 

11.1

MM-1- Mandirhasaud-New Raipur (New line)(20Km)

(i)Detailed estimatefor newRaipur Mandir hasaud – Kendri new line (20 Km.) has been sanctioned by Railway Board on 30.10.12 at the cost of Rs 100.00 Cr. as Istmaterial modification. Cost ofproject is shared by State Government in the form of providing land free of cost, constructing stations & bearing full cost of ROB/RUB in Naya Raipur area. Draft MOU has been sent to NRDA for approval on 24.02.2014 but insteaded of approving MOU sent by Railway,NRDA sent there own MOU which is to be submitted back to NRDA with Railway’s observations.

(ii). Land is being acquired by New Raipur Development Authority (NRDA) and 54.693hec. Out of 111.81Hect of land has been handed over to Railway and for balance land NRDA is processing for acquisition.

(iii (iii)(iii)In 2014-15 no fund was allocated. Subsequently Railway Board vide letter dated 24.11.14 has re appropriated Rs 5 Cr. accordingly tender opened on 4.2.2015.During 2015-16 RVNL has been given Rs.341 Cr. therefore Railway Boad was requested on 21.4.15 for providing Rs.15 Cr. for above work, Railway Board vide letter No.2015-B-106 dated 26.6.15 allotted Rs 5.00Cr. after re appropriation .

(iv)Detailed estimate for Construction of ROB/RUBs in connection with Mandirhasaud Naya Raipur- kendri new line (Under Deposit) is sanctionedon 01.01.15 ( Rs.3719.84 lakhs). NRDA deposited ofRs.10 Cr. for thiswork on 02.01.15.Tender opened on 04.02.15 which is under finalization

 

11.2

MM-2-Kendri – Dhamtari including Abhanpur – Rajim (67.20 Km) GC.

Detailed estimate ofRs 582.42 Croresbetween Kendri – Dhamtari, Abhanpur – Rajim Gauge conversion has been submitted to Railway Board on 10.02.15 for sanction.For above work Railway Board had been requested on 21.4.15 for providing Rs.5 Cr. for land acquisition and other related works.

12.0

Kalumna – Nagpur

The work was sanctioned in2007-08 with an abstract cost of 21.00Cr. Detailed estimate cost was Rs 24.78 Cr.(25.9.11) Revisedcostis Rs. 38.26 Cr under process of submission to Railway Board.

Section commissioning is held up due to non removal of 190 encroachments in 900m length near Nagpur.


Chief secretary /Maharastra in a meeting held on 22.1.13 with Railways andDistrict authoritieshad advised that no encroachment removal shall be done unless Railway comes up with theRe-habilitation plan. Further Chief secretary /Maharastra has also been requested vide CAO/C/SECR’s letter dated 13.03.13 Again letter written to Divisional Commissioner,Nagpur, Maharashtra on29.01.2014 followed by remainder for early removal of encroachment.

DRM/SECR/NGP conveyed that these encroactment are likely be removed shortly.. all the works except the 900m of encroached land had been completed long ago. Tender forEngineeringand S&T have beenopenedand under finalization. Electrical tender willopen on 5.8.2015

13.0

Champa – Jharsuguda 3rd line (165 Km ),

The work was sanctioned in2008-09 with a abstract cost of Rs.872.12 Cr.Detailed estimate sanctioned for Rs.983.40 Crore on 30.3.2012 Railway Board vide letter No.2015-B-106 dated 26.6.15,B.G reduced ofRs 5.00Cr. after re appropriation

All tenders for Civil between Champa-Kharsia-Raigarh are awarded. Earth work and minor bridge completed between Champa-Kharsia. Work on four major bridges is also in progress. P-Way linking work is in progress.

Tender for earth work & minor Bridges between RIG and JMG awarded. Tender for ballast supply between RIG-JMGis opened on 2nd june 2015. Tenders between JMG-JSG for earth work minor Bridges are terminated, reinvited and price bid opened on 21-05-2015.Tender discharged & to be reinvited. Tenders for Major Bridges terminated and reinvited. Tenders for OHE work of Champa –Kharsia awarded on 15.10.2014.. S&T Tender forChampa/EI awarded on 31.7.14 and forJDI PI awardedon 26.8.2014.Tender for modification in existing EI (Saragaon- Deori, Baraduar ,Sakti & Kharsia awarded on 25.09.2014. Tender for transportation of Girder from MMR workshop finalized. Tender for shifting of IBS goomityawarded on 12.08.2014.

Progress ofthe project.

(a)Earth work of 14.86 lakh cum completed out of 22.65 lakh Cum

(b) Minor bridges 84 completed out of 120 Nos.

©Major bridges 8 completed out of 18 Nos

(d) Ballast 2.80 lakh cum completed out of 4.64 lakh cum.

(e) Track linking-NIL.

In the 1 st stage part portion from Champa Kharsia 46Km covering 4 block sections is proposed to be completed by Dec.15 . It is proposed to complete entire Project (152 Km) by Dec.2017

 

14.0

Durg - Rajnandgaon 3rd line (30.80Km)

The work was sanctioned in2010-11 with abstract cost 147.06 Cr. Detailed estimate for Rs.152.99 Cr sanctioned in Oct.10.Revisedestimatefor Rs 231.68 Cr. Vetted by accounts on 15.05.15 and under process.

Land –(i) Private land(0.619 Hect)-Durg district-0.428 hect. and Rajnandgaon district-0.191hect has alreadybeen handed over to Railway. Further for acquisition of 0.505 Hact Pvt in Durg district necessitated to adjust approach curve on HWH end of Shivnath river, application has been submitted to Collector/Durg on 21.05.14 which is under process and demand note of31,05,938/- for pvt land of 0.505 has been received fromCollector Durg on 26.05.15 and submitted on 12.6.15.

(ii)Govt. land (0.907 hect.)- Durg district-0.834hect. and Rajnandgaon district-0.073 hect formalities under process by the State Govt.


Progress-

(a)Earth work of 4.98 lakh cum completed out of 11.11 lakh Cum

(b) Minor bridges 7 completed out of 20 Nos.

(c) Ballast 0.84 lakh cum completed out of 0.82 lakh cum.

 

(e) Track linking-NIL.

Tender for Girder transportation from Civil Engg Workshop, Central Railway/MANMAD is finalized on 9.1.2015.Tender for earth work and minor bridges in Muriphar-Rajnandgaon sectionopened on 28.1.2015 is under finalization. Physical progress-27%.Completion is planned in two phases,Durg- Muriphar -31.12.2016 and Muriphar-Rajnandgaon-31.03.2017.

 

 

15.0

TRAFFIC FACILITIES & THROUGH PUT ENHANCEMENT WORKS

As per Pink Book 2015-16,total 27works executed by Construction Organization, details are as under

Details

Nos

No of Pink Bookworks being executed by Construction Organization

27

No. of works completed up to 31.03.15

4

Target for completion in 2015-16

8

Other than targeted work in progress

15

Work completed in 2015-16

0

 

16.0

 

ROB/RUB works

38 nos ROB/RUB Pink Book works and one deposit work are being executed by Construction Organisation The details are given in Annexure – V (B

17.0

PROGRESS OF SURVEYS

Detailed progress of survey works is given in Annexure –IX

18.0

AREAS OF CONCERN

The completion of Kalumna – Nagpurdoubling isaffecteddueto non - removal of 190 encroachments near Nagpur junction area over a length of900m.Draft letter from Hon’ble MR toC.M/Maharastra and from CRB/ Railway Board to Chief Secretary has been sent to Railway Board on 8.6.2015 for early removal of encroachments.

 

19.0

ASSISTANCE REQUIRED

19.1

Early sanction of following estimates is requested

 

(a) 2nd Revised Estimate of Chhindwara - Nagpur(149.522 KM)Gauge conversion

costing of Rs 1085.10 Cr submitted to Railway Board on 23.12.2014.

 

(b) The detailed estimate of Rowghat-Jagdalpur Phase -II costing of Rs 1702 Crsubmitted

to Railway Board on 28.1.2015

 

(c) Revised detailed estimate of ROB at Tumsar in lieu of LC No. 532, costing of Rs 36.93

Cr. submitted to Railway Boardon 27.02.2015

 

(d) Detailed estimate of Wadsa-Gadhchiroli New BG Line (52.36 Km) costing of 403.00 Cr

submitted to Railway Board on 17.04.2015 aftercomplying all the observation of Railway

Board.

20.0

In view of increased B.G from 511.46 Cr to 2072.40 Cr (CAP+EBR) for 2015-16, followingadditional officers will be requiredby SECR Construction organization

a) SAG (Engg.)-1 No

b) JAG -5 Nos (Engg.-2,S&T-1,Electrical-1 & Accounts-1

 

 

 

 

 

 

 

 

 

 

 

Important Projects

 


Plan Head -11 New Line

Sr No.

Name of project

Cost in Cr.

Progress

Over all %age of progress

TDC

1

Dallirajhara -Jagdalpur(235 Kms),

Phase-I-631.78

 

The work is sanctioned in 1998-99 The entire project is to be executed in 2 phases.Phase – I (95 Km) between Dallirajahara - Rowghat –This work is executed byRVNL funded by SAILPhase –II (140 km) between Rowghat to Jagdalpur Being executed by Railwayfunded by Railway , NMDC and CG Govt Presently contract for roadbed & Bridges (Dallirajhara-Keoti 42 km) had been awarded and work in progress,

 

18.50 for Phase-I

31.10.16

2

Wadsa – Gadchiroli(49.5Km

232.40

The work is sanctioned in 2011-12 Detailed estimate submitted to Railway Board. on 08.07.2014 for sanction

 

0

31.12.2020

 

3

Raigarh (Mand Colliery) - Bhupdeopur (63 km)-

379.08

The work is sanctioned in 2013-14 under EBR. and executed by IRCON. Land acquisition is done through SECR. Notification under Clause 37A issued by Railway Board on 17.12.2013 declaring above project as Special Railway Project. Further Clause 7A of Section 2 had been published on 28.02.14 and Section 20A Sub Section (1) has been signed by GM/SECR on 14.03.14 and published on 30.04.2014. DPR for 104 Kmsubmitted by IRCON and same is submitted to Board on 19.8.14 for sanction.

 

0

 

4

Gevra Road - Pendra Road (121.70 km)-

838.02

The work is sanctioned in 2013-14 under EBR and executed by IRCON. Land acquisition is done through SECR. Notification under Clause 37A issued by Railway Board on 17.12.2013 declaring above project also as Special Railway Project. Further Clause 7A of Section 2 had been signed by GM/SECR on 14.03.14 and published on 25.03.2014 and Section 20A Sub Section (1) has been signed by GM/SECR on 06.05.14 and published on 21.5.14.

 

0

 

 

Plan Head -14 Gauge Conversion

 

1

Jabalpur- Gondia incl. Balaghat – Katangi(285 km

1037.90

 

The work is sanctioned in 1996-97 Gondia-Balaghat Section including MOILsiding (49 Kms) - Commissioned on 06.09.2005 & Balaghat- Katangi section:(46.8 km) was commissionedon 23.02.10.

 

Work in progress in Jabalpur –Nainpur while work is held up between Balaghat –Nainpur section pendingforest clearance from MOEF/New Delhi. The proposal for reconsideration of forest land in Balaghat district has been submitted by Railway on 08.01.2014 and joint inspection done on 19.08.14. Clearance is awaited. It is proposed to open Jabalpur-Nainpur Section (115 Km) early.

 

69

31.12.2019

2

Chhindwara - Nagpur(149.522 KM

663.66

Work sanction in 2005-06, work is going on at fast pace, in view of good progress and high priority of the project, it is proposed to open Chhindwara –Nagpur Section for BG in one go.

 

70

31.12.2016

3

Chhindwara - Mandla Fort (182.25 Km

737.72

This work sanctioned in 2010-11. work is in progress in Chhindwara-Nainpur-Mandla fort section. However progress is slow due to less budget allotment.

 

7

31.12.2018

 

Plan Head -15 Doubling work

 

1

Champa – Jharsuguda 3rd line (152.38 Km

983.40

Work sanctioned in 2008-09. work is going on very fast . In first phase Champa-Khrasia(46 Km) section is proposed to be completed by Dec’2015.

 

24

31.12.2017

2

Durg - Rajnandgaon 3rd line (30 Km

152.99

Work sanctioned in 2010-11. Work is in progress.

24

31.03.2017

3(a)

Mandirhasaud /New Raipur-Kendri New line (20.00 km

100.00

The project is sanctioned in 2010-11 as Istmaterial modification to Raipur- Titlagarh doubling of East CoastRailway. Cost ofproject is shared by State Government in the form of providing land free of cost.

 

0

 

3(b)

(i)Kendri - Dhamtari including abhanpur - rajim (67.20 km.) gauge conversion sanctioned as material modification to raipur- titlagarh doubling of east cost railway

 

283.85

The project is sanctioned in 2011-12 as material modification to Raipur- Titlagarh Doubling of east coast railwayDetail estimateof this project will be sent to railway Board for sanctioned shortly

0

 

4

Kalumna – Nagpur doubling work-

 

24.59

Work sanctioned in 2007-08.work is held up due to encroachments near Nagpur.

 

85

30.06.2015

 




Source : South East Central Railway CMS Team Last Reviewed on: 04-08-2015  


  Railnet Mail Login | Admin Login | Site Map | Contact Us | RTI | Disclaimer | Terms & Conditions | Privacy Policy Valid CSS! Valid XHTML 1.0 Strict

© 2016  All Rights Reserved.

This is the Portal of Indian Railways, developed with an objective to enable a single window access to information and services being provided by the various Indian Railways entities. The content in this Portal is the result of a collaborative effort of various Indian Railways Entities and Departments Maintained by CRIS, Ministry of Railways, Government of India.